224 ALARNG Fort McClellan Transient Training Barracks, Anniston AL

Project: Ft. McClellan Transient Training Enlisted Barracks

Contact: Larry Crawley

Phone: (334) 271-7464

This project consists of demolition, new Construction, and extensive site work. The demolition included thirty existing structures, including asbestos containing material removal. The new construction included 3 two-story buildings, 2 one-story buildings, 2 dining facilities, 2 supply administration buildings, 1 battalion headquarters building, and relocation of a 25-foot by 80 foot pavilion. Eight of the ten buildings use Geothermal wells for heating and cooling. CCI had to re-grade the entire site, which encompassed approximately 25 acres. The site work included storm drainage, sanitary sewer, domestic and fire water, as well as gas and electrical. The buildings contained the following special finishes: epoxy floors, stained and sealed concrete, and polished concrete floors.

Year Completed: 80% complete with completion date scheduled for December 2023

Total Cost: $34,664,917.25

Posted in

Carmon Construction Inc.